Do the following steps:
. Go to Roadmap view.
. Create Epic
. Create tasks inside the Epic from the side view.
. Go to Board View.
. None of the tasks, nor the epics, show in the boards.
. If I go to Backlog, they are all there. But there is no option to enable them to be active in the board I guess?
I am trying to make sense of this but it just doesn't make sense. Can anyone explain it to me? Thank you.
Hello @juan ,
Traditionally, teams that work in a Kanban style don’t use a backlog. If you work in a Kanban style, you can still help your team prioritize upcoming work with a backlog. We call this style of working Kanplan, where your backlog keeps track of tasks that you want to do in the future and cleans up your board’s to-do column.
Therefore, if you want Epic and tasks to appear directly in the board after creation, you need to disable Backlog in Features.
https://support.atlassian.com/jira-software-cloud/docs/enable-the-backlog/
https://support.atlassian.com/jira-software-cloud/docs/enable-sprints/
Hello Ollie. That's it! Thank you. The issue can be solved with the link below:
Where it says:
To move issues from the Backlog list or planned sprints list onto your board:
Drag and drop issues from the Backlog list into the Board list (if you work in a Kanban style), or into your team’s active sprint list (if you work in a Scrum style using the Sprints feature).
On your board, your issues will display in the column corresponding to their current status.