Multiple Active Sprint in JIRA Next-Gen

Noppadon
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 19, 2021

Hi 

I use the  JIRA Next-Gen it can not use Multiple Active Sprint.

I have question below 

  • Can we convert JIRA Next-Gen to classic version because classic version can use Multiple Active Sprint.
  • How to config Multiple Active Sprint work on JIRA Next-Gen 

 

1 answer

1 accepted

0 votes
Answer accepted
KAGITHALA BABU ANVESH
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 19, 2021

Hi @Noppadon ,

you can't run multiple sprints in Next gen project. the option is not available.

Please check the below link for migration of projects in Jira cloud

Next gen to classic migration 

Noppadon
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 19, 2021

Thank you so much.