I am trying to move a story from an epic to current sprint. The particular story is not showing up in backlog. What options do i have to move that story to a particular sprint.
If a story is not in a backlog, it will not be able to appear on the associated board as well (a backlog is a part of a board, and they select the same set of issues)
You will need to amend the issue, changing it so that the board and backlog select it, or amend the board's filter so that it selects it.
Hi @Sravani Madala and welcome to the community!
I'm not sure I understand your intent here so I'll give two options depending upon your meaning:
Hope this helps.