I have set up a Kanban, Company Managed project and on the Kanban board itself I can see columns 'Backlog' 'Selected for Development' 'In Progress' and 'Done' but I cannot work out why I can't see backlog on the left hand panel ie below 'Timeline'. Is anyone able to assist me please? Is it because it is a Kanban Project which means I don't get that view? Thanks
Just in case anyone else finds this question, the Backlog is an optional setting for Kanban Boards.
To add it, you need to be a Board Admin, and then...
^ This will add the Backlog. The Statuses in this column will only display in the Backlog tab from now on.
You can also activate the "Epics Panel" from the Columns screen, if you'd like this to be visible on the Backlog. Deactivating this setting allows Epics to be visible on the board as cards.
Ste
Actually I have just answered my own question - via board settings!