Hello,
We are preparing to migrate from Jira Data Center to Jira Government Cloud and are looking for timeline estimates from others who have completed migrations of a similar size.
Environment details:
Jira Data Center Version 9.12.31 (Soon to be on 10.3.19)
1-node Jira Data Center deployment
~400 projects
~410,000 issues
~1,300 users
~700 custom fields
12 installed apps total; 4 apps will be migrated (Email This Issue, BigPicture, Jira Workflow Toolbox, EazyBI)
Identity and access:
SCIM provisioning will be used
SSO is already fully configured
Environments:
3 Jira environments (1 production, 2 non-production)
Both non-production environments contain non-production data
Additional context:
Only 4 apps will migrate; the remaining apps will not be brought to Cloud.
---> We are seeking general expectations on how long migrations of this scale have taken (for example: 3 months, 6 months, 9 months, etc.)
We would appreciate any examples, guidance, or ranges based on past migrations of a comparable size, including time needed for planning, test runs, validation, and final cutover.
Thank you
Hi @Lawrence
The timeline on how many months it'll take is tricky. You have:
1. Customer timeline (Jira DC licenses, app licenses, other business priorities that impact how soon you need to move to cloud)
2. downtime to test migration ( you only have one node, which limits when you can migrate and test)
Roughly, it can be 3 to 6 months. leave plenty of time for UAT1, UAT2, test, test and tes. I can't stress this enough. test!
---
For this, you are missing what it takes the most, the attachments. 1 TB can take 15-20 hours.
~400 projects
~410,000 issues
~1,300 users
~700 custom fields
The data could take 3-5 hours.
There is a lot of docs that will help you test the migration (there is a lot to fix before testing)
https://confluence.atlassian.com/adminjiraserver/increasing-jira-application-memory-938847654.html
---
And now APPS!!
Understand and read how to migrate each app to cloud(some of them have an easy path using JCMA, others not su much)
https://apps.decadis.net/spaces/JWTCLOUD/pages/62882489/Migrate+JWT+DC+to+JWT+Cloud
1. Open a ticket with each vendor. They can guide you and will happily do so.
Good luck!