Median between two statuses

Yuliia Zhyliaieva
Contributor
May 19, 2020

Hi! I need to calculate a median between two statuses in Support Issues workflow.

The built-in functionality of Control Chart does not work for me, because the issues move from one project to another. The projects share workflows, but the control chart provides info only per 1 project.

Is there a way for me to report a median in days between two statuses (not status categories)?

Thanks in advance! 

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 20, 2020

Why are you moving issues between projects?  That suggests a broken process (one that control charts can't report on because it's broken)

Yuliia Zhyliaieva
Contributor
May 20, 2020

Yeah, this is for support bugs that are first processed by support team and QAs, and only then moved to the development team. When we set up the processed, we never knew about the outcomes of this decision. So, is there any workaround for me to get the median right now?

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 20, 2020

There is no way to "work-around" a broken process.  You need to fix the process, not the reporting.