Managing Sprint across two boards in two different projects

Dileep Goyal
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 7, 2019

I have two different boards. Board A and Board B under project A and project B, respectively. I have created tasks under Board A and Board B. 

Now I am creating a sprint under Board A in Project A. How can I add the tasks from Board B from Project B in the same sprint so it shows up as part of same sprint and can create dependency between tasks in Board A and B and both projects. 

FYI: when I assign Tasks from Board A and Board B to same epic, it shows up under one epic but similar behavior does not happen for sprint. 

is there a different way i should set up my sprint?

1 answer

1 accepted

1 vote
Answer accepted
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 7, 2019

Hello,

Your board A must select issues from Board B. You need to modify the filter for the board A (board settings -> general). After it you can create a sprint in board A and include issues from board B.

Dileep Goyal
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 8, 2019

Thanks Alexey