I have two different boards. Board A and Board B under project A and project B, respectively. I have created tasks under Board A and Board B.
Now I am creating a sprint under Board A in Project A. How can I add the tasks from Board B from Project B in the same sprint so it shows up as part of same sprint and can create dependency between tasks in Board A and B and both projects.
FYI: when I assign Tasks from Board A and Board B to same epic, it shows up under one epic but similar behavior does not happen for sprint.
is there a different way i should set up my sprint?
Hello,
Your board A must select issues from Board B. You need to modify the filter for the board A (board settings -> general). After it you can create a sprint in board A and include issues from board B.
Thanks Alexey