Greetings, Community!
I was wondering, if anyone knows of solutions or plugins to display two timelines for one issue on the Roadmap?
We are using a work management project as a marketing planner.
And the two dates differ - start of work on the campaign and start of the actual campaign.
Out of the box solution with the timeline allows to account only for one start date, which leaves us at disadvantage (either we track only project overview or only the campaign overview).
Is there any add-on with more complex timelines for the same issue?
Hi Dmitry,
No this is not possible to show two or more timelines for a single issue. You can have start and due dates, but not multiple start dates. You might consider two different issues for the work.
Atlassian Government Cloud has achieved FedRAMP Authorization at the Moderate level! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.
Register NowOnline forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.