Jira Kanban Board - Done story points not populating on story point estimate for sprints!!

Sharam Blouri June 27, 2022

02200eff-a1e2-4a3e-9bb7-8d04e2dad284.png

does anyone know what the problem is?

2 answers

0 votes
Sharam Blouri June 28, 2022

shure here:

55.png

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 27, 2022

Are the issues that are done in the sprint in the very last (rightmost) column of the active sprint board?

Sharam Blouri June 28, 2022

yes..

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 28, 2022

Could you show us one of the done issues?  (obscure the text and user fields if you want, we're only interested in the structural stuff like estimates, status, resolution and type)

Sharam Blouri June 28, 2022

shure here:

55.png

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 28, 2022

Ok, that looks good, but can you confirm that the "5" on it is a story point value and your board is set to use that field for the estimation?  Also, can you confirm that that issue is not a sub-task?