I have two projects: CUS (Real one) and CPT (My Test one).
I have a rule which, when epic is created, it creates a task and then links that task to the epic.
In my CUS project, this does not work. Task is created but no epic-linking.
In CPT it works perfectly.
I'm really lost with this.
The left hand one works, the right does now.
The rule
Hi Crispin - Welcome to the Atlassian Community!
In the Epic Link update field for Set value, type:
{{triggerIssue.key}}
Be sure to click on what you typed so it will actually stick it in the field.
That should work for you.
Because you were copying from the Issue (the child itself) and not the Trigger Issue (the Epic).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Because it might have been the same project.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Crispin ,
This is strange.
And when you use "Copy from Triggerissue" , is this working on both rules?
Or
Regards, Marco
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.