Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Jira Automation - Planning tasks automatically by Due date to the sprint backlog

Dominik Trunk
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 24, 2021

Hi, 

our team would like to switch from Kanban to Scrum in perspective. Unfortunately, we have the problem that we often wait for an external input from our collaboration partners, which leads to periods of waiting. Right now, these waiting tasks sit on the Kanban in the "waiting" lane for a while until the external partner has completed their ToDo. This disturbs a bit our board and absolutely does not fit with the planned Scrum process.

So we are now looking for a better solution to organize these waiting times in Scrum. 

One idea we had was to split the activities. First we have a task to bring all the information to the external partner and then we have a second task to remind the external partner some weeks later. This second task stays in the backlog and it would be really helpful if we had some kind of automation with a dependency on the due date. As a result, the reminder task will stay in the backlog until the due date of the task occurs. When the task is due, it should be automatically moved to the next Sprint Backlog. 

Do you know any solutions or similar use cases that can help us to implement this in Jira?

Thank you very much and best regards, 
Dominik  

1 answer

1 accepted

1 vote
Answer accepted
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 24, 2021

Hi @Dominik Trunk -- Welcome to the Atlassian Community!

You *could* create a rule, triggered on sprint creation which checks for any issues with due dates during the sprint timeframe, and take action.  Rather than adding such issues automatically to the sprint, you may instead want to notify the team to consider their capacity and the "due date" issues for inclusion in the sprint.

Another option is a scheduled trigger rule, which checks for issues due in the next week, or so, and notifies the team to consider actions/next steps.

Kind regards,
Bill

Dominik Trunk
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 24, 2021

Hi @Bill Sheboy , 

thank you for your suggestions. I think the solution no. 1 could work for us. I'll try this. 

Best, 
Dominik 

Like Bill Sheboy likes this

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
TAGS
AUG Leaders

Atlassian Community Events