I'm trying to view the Predicted Completion date in the Agile Version Report graph. But the graph only shows up to the current date, and not up to the Predicted Completion date.
I'm using Jira OnDemand 6.2-OD-01. Please advise how I can see the Predicted Completion Date. I've attached sample screenshots below:
Currently I'm seeing this:
But I want to see something like this. Note the dates go into the future.
Answer: you need to complete 10% of work before the estimated completion date will appear.
wow... that would be something that should be shown on the chart as long as it doesn't start estimating. Drove me nuts ;-)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Would be useful if the description of the report actually gave that detail - just added a bunch of stories to a release and the prediction disappeared - unfathomably
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Atlassian Government Cloud has achieved FedRAMP Authorization at the Moderate level! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.
Register NowOnline forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.