Hi
I think you're confusing different parts of the platform - above you have...
- Workflow: A set of Statuses, of which one is Backlog
- Scrum Board: A visualisation of your issues - with these components...
- Board Columns: These are the columns on your active Sprint Board. One is called To Do - but columns can reflect one or more Statuses, and might not be named the same as the Statuses themselves
- Backlog + Sprints: The backlog, and the sprints, are not linked to Statuses natively
So as an example, if TESTSCI-9 needs to be in a Sprint, and change Status - you might need to...
- Change the Status on the Issue (or drag it between columns, if not in the same one)
- Drag it into the future sprint
...as two individual actions
I would recommend...
- Reviewing how Scrum Boards (and boards in general) work - check-out this help page for more information
- Review your Workflows - if having Statuses, Columns, and Backlog/Sprints with similar names is confusing
- Review your Board design, for the same reasons
- Consider if Automation might be useful for your team - so those two individual actions above could become one. For example, you could have a rule which states...
- If TESTSCI-9 is added to a future sprint...
- Then change its status from Backlog > To Do automatically
Let us know if you need any further help with this :)
Ste