Issue when registering time sheet

Toni Arcas
Contributor
August 25, 2021

HI all!

I'm experiencing a problem when a user is registering hours in a specific task.

If I need to register more than 1 day, then all the hours are automatically assigned to the start date, which is not realistic, so I must assign the time day by day.

As an example, if i want to assign 40 hours (from monday 9th of August to friday 13th of August, considering 8 hours/day) to the same task, then I submit 40 hours with starting date monday, but all 40 hours are assigned to Monday.

When I chek the timesheets, or by apps like "Worklogs", the rest of the week is empty.

Do you have any suggestion? May I change any setting somewhere?

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 25, 2021

This sounds like your people are using very simple logging and understanding that they should be logging by day rather than week.

For a week's work for me, I log 8 hours per working day.  In my case, I'm usually jumping around across many things, but sometimes, I do a full week of project work.  So, that should be 40 hours a week, but because my timesheet is daily, I log 8 hours per day - five worklogs which are identical barring their date.

If you want to assign 8 hours a day for a week, you need to be logging daily.

(Note that I have a nice cheat for this - we use Tempo timesheets, where you can tick a box for "period", giving it a start and end date, and I give it "8 hours, stuff for client, start monday, end friday" and it creates 5 separate logs for me)