When creating issues from my advanced roadmap view, I'm only able to create the following types:
Initiative, epic, story
However, the board it is linked to also contains both 'Task' and 'Subtask' issue types.
These show up on the roadmap just fine, I just cant create them from there
Is there something I am missing to enable this?
Hi @jakob dall ~ do you have a filter applied in your hierarchy? i.e. Epic to Story? You won't be able to create an issue if that hierarchy is filtered above the level you want to create an issue in. Are there other filters applied in your Plan that may be contributing?
No, I have no filters active. And I'm showing all issues from Initiative to Sub-Task
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @jakob dall ~ try this: Click Create Issue > select Story and to the left of where you enter the Summary, you should see the issue type icon with a drop-down (see below). Click that and you should see the Task option (provided there is nothing else preventing this from being visible). I tried this and it worked for me....
As for sub-task, that needs to be created from clicking the 3 ellipses next to the parent (see below).