Issue dependencies set up prior to working in Timeline do not seem to show up in Timeline

Cox_ Paul
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 11, 2025

I have a number of issues which I have linked together to show the flow required in order to make a final decision and I have done this prior to working in the Timeline view. When starting to work in Timeline view, I would have thought the dependencies previously set up would automatically be illustrated in Timeline but that appears to not be the case and i have to manually add them. 

Is this really the case or am I missing something?

1 answer

0 votes
Trudy Claspill
Community Champion
March 11, 2025

Hello @Cox_ Paul 

Welcome to the Atlassian community.

Are you working on a Timeline view that is art of a Plan that you created through the Plans menu? Or are you looking at the basic Timeline view available when you view A scrum or Kanban board that references only one project?

How did you define the dependencies? What link type did you use to link the issues to each other?

If you did not use the blocks/is-blocked-by link, that is most likely the problem.

If you did use the Blocks link type then my next question would be are the links between issues that are all within the scope of the Timeline source data?

Trudy Claspill
Community Champion
April 2, 2025

Hello @Cox_ Paul 

Were you able to resolve your issue with the information I provided? If so, please consider clicking on the Accept Answer button to mark your Question as Solved.

If you still have questions on this topic, please let us know.

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
TAGS
AUG Leaders

Atlassian Community Events