Is there a way to remove the option to put time estimation on stories?

Eleanor
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 12, 2023

Is there a way to remove the option to put time estimation on stories? (put the time estimation only on the sub-tasks of the story) 

1 answer

0 votes
Mark Segall
Community Champion
July 12, 2023

Hi @Eleanor and welcome to the community!

Yes - This can be done by updating the respective screens.  On the Story screen, you would remove the time field(s) in question (Time Tracking, Original Estimate, etc.) and on the Sub-Task screen you would add the field(s).