Is there a way to number sub-tasks so that they relate back to the issue they support?

Stanislav
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 8, 2020

Hi Team,

Just looking for the answer on the subtask number creation. If there is a way to have the subtasks generate a sub number to the project e.g. - project is VISD-10 and has several subtasks - could they be VISD -10.1, VISD - 10.2, and VISD -10.3 etc ?

Thanks in advance 

1 answer

1 accepted

0 votes
Answer accepted
Zoi Raskou
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 8, 2020

Hello, no this is not supported. Sub-tasks are allocated an issue key just like any other issue type which comes from the database. They do have an identifier though. If you look into an issue with sub-tasks you will find a column where the sub-tasks are numbered. 

Stanislav
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 8, 2020

ohh..