Here is what I want to do:
I have two epics. I need to get one epic completed before the other. Both epics have start and end dates. After I have linked the epics and created a dependency, when I move the first epic further out, the epic that is dependent on it, does not update its start time. Is there a solution for this?
Hello @Dave Levine
Welcome to the community.
Disclaimer: I've not used Advanced Roadmaps, but I'm about to make a suggestion based on it.
Have you looked at the Auto-Schedule feature of Advanced Roadmaps to see if that addresses your use case?