Is there a way to have dependency epics and issues adjust when you update start and end time?

Dave Levine
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 28, 2021

Here is what I want to do:

I have two epics. I need to get one epic completed before the other. Both epics have start and end dates. After I have linked the epics and created a dependency, when I move the first epic further out, the epic that is dependent on it, does not update its start time. Is there a solution for this?

1 answer

1 accepted

0 votes
Answer accepted
Trudy Claspill
Community Champion
October 28, 2021

Hello @Dave Levine 

Welcome to the community.

Disclaimer: I've not used Advanced Roadmaps, but I'm about to make a suggestion based on it.

Have you looked at the Auto-Schedule feature of Advanced Roadmaps to see if that addresses your use case?

https://support.atlassian.com/jira-software-cloud/docs/auto-schedule-issues-on-your-advanced-roadmaps-timeline/