I am working on project which include two difffrent teams but we have single project .
The single burndown chart is created to determine the velocity of overall project and team. Is it possible to create two diffrent burndown charts based on team A or team B . Currently we are using the component to diffrenciate diffrent teams ?
Hi @Ritesh
So if you create 2 boards, using the filter from the project, but for one board you add
component=TeamA to the filter and for the other you add component=TeamB.
Each board would then show the burndown for just that team's tickets, and the project would have the overall burndown.