Is it possible to change the format of "Estimated Time to complete" field?

david.d.barnett
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 5, 2020

I would like to be able to change the format of "Estimated Time to complete" field from date-time, to just days (e.g. 5d, etc.). If it is possible, then would you kindly point me to the documentation to support this task?

Regards,

Dwayne

1 answer

0 votes
Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
November 6, 2020

Hello Dwayne,

Welcome to the Atlassian Community!

The format of the default time tracking fields of Jira Cloud Application can be changed by navigating to Jira settings > Issues > Time tracking, as described in the documentation below:

Configure time tracking 

The default time tracking fields are: "Original estimate", "Remaining Estimate" and "Time Spent", all the three fields are managed on the page mentioned above.

That being said, there is no "Estimated Time to complete" between the default time tracking fields, so I'm wondering if you are referring to a custom field provided by a third-party app. Can you confirm it?

If possible, please provide us with a screenshot of the mentioned field so we can better understand your request.

Let us know if you have any questions about the time tracking feature.