In the summary tab is a status overview. A pie chart showing all the work per status.
We have noticed that e.g. the work items in status CLOSURE are decreasing although nothing was changed to the issues within the project (we checked using update date)
How is it possible that the amount of CLOSURE defects is decreasing in the pie chart when nothing changed?
Hello @Dimitri De Smaels
Welcome to the Atlassian community.
As per the documentation:
https://support.atlassian.com/jira-software-cloud/docs/what-is-the-summary-view/
...only items completed within the last 2 weeks will appear in the count of completed items.