In my Jira Software I have project "Done", but is still in "TO DO"

Jaroslav Jasek
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 21, 2023

Hello,
Can anybody help me, why In my Jira Software I have project "Done", but is still in "TO DO" ?
abi_jira1.jpg

1 answer

2 votes
Mikael Sandberg
Community Champion
July 21, 2023

Hi @Jaroslav Jasek,

Welcome to Atlassian Community!

Have a look at your board mappings, each status is mapped to a column on the board, and in this case it looks like you mapped Done status to your To Do column. Just click on the three-dot menu on the board and select Columns, from there you can do the mapping. 