In JIRA, when Time Control is enabled, as the person records the time on a task, the Story Points ar

Adilson Junior
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 18, 2021

Hello good Morning.

In JIRA, when Time Control is enabled, as the person records the time on a task, the Story Points are burned and the burn down is updated?

If so, how does JIRA calculate the number of Story Points to be burned based on the number of hours launched? Based on what and how is this calculation done?

I thank the attention.

Thanks!

1 answer

0 votes
Alexis Robert
Community Champion
February 18, 2021

Hi @Adilson Junior , 

 

there are no links between time spent on an issue and Story Points burdown : the burndown chart is only decreased when an issue is resolved.

 

Let me know if this helps, 

 

--Alexis

Adilson Junior
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 18, 2021

Thanks!