I want to move couple of features from one Increment to the next.

Mirjana Popova January 12, 2024

I had to move couple of Features from the current Increment to the next Increment, I changed the labels and Sprints. Now I can see them in both increments.

What will be the correct way to move them from one increment to the other.

 

 

1 answer

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 12, 2024

Welcome to the Atlassian Community!

You can not do this for some issues.  Only issues that have never been in an active sprint can be moved.

The sprint field contains all the sprints an issue has been in, not just the current one.  It has to, in order to report accurately.

If you have an issue that is in an active sprint which is in PI1, then when you include it in a sprint in PI2, it's rightly going to appear in both PIs.