I'm the admin of this project. And Sprint feature is enabled.
Today I found out that the the completed work link in Burnup report is 0.
I want to change the definition of "Completed" in Burnup report.
Can Configuring estimation and tracking do that?
How do I do that?
"Completed" in Jira Software means "issues in the right hand column of the board ". You can't change that. You can change what the estimates are done on - story points, estimates or any numeric custom field can be used (with the caveat that they're not for sub-tasks, so Jira will ignore them)