Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to seperate issue timeline from epic timeline

Jawad Jakhjoukh
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 1, 2024

Hi all,

I would like to separate the visual timeline that is shown for the issue from the timeline of the Epic. The issues have different start and due dates, but they copy the timeline of the epic they're under or the sprint they're under as you can see. In this example 'Issue 3' has a different start and due date than 'Project 1' yet the visual timeline for Issue 3 is not correct (due date is february)  How do we accomplish this?

Schermafbeelding 2024-02-01 144704.pngSchermafbeelding 2024-02-01 145217.png

1 answer

1 accepted

1 vote
Answer accepted
Trudy Claspill
Community Champion
February 1, 2024

Hello @Jawad Jakhjoukh 

Above the Timeline in the upper right corner click on the ... button and select Configure Timeline.

Screenshot 2024-02-01 at 2.59.34 PM.png

 

Then scroll down to the Child Level Issue Scheduling and make sure you have selected Schedule child issues by dates

 

Screenshot 2024-02-01 at 3.00.11 PM.png

Jawad Jakhjoukh
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 5, 2024

Thanks a lot!

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
TAGS
AUG Leaders

Atlassian Community Events