Hello,
I’ve recently reorganized our tasks by creating epics and dragging the relevant tasks under each corresponding epic.
However, I noticed that even after doing so, the tasks (e.g., WCE-41, WCE-93, WCE-37, WCE-36) are still showing up separately in the main project list view — in addition to appearing under their respective epics.
Could anyone advise how I can ensure that these tasks are displayed only once, ideally under the epic view only, and not duplicated in the main list?
Thanks!
Hello @Sedo YI Welcome to the community!
Assuming you are using project timeline view and in this case ensure you should select the Hierarchy From EPIC to STORY in the Filter.
Note: Make sure that each task should have its respective parent to be selected.
The same applicable for plans as well and if you are not using Timeline then please share your snpa so that it help us to check and assist you accordingly.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.