How to remove duplicated tasks

Sedo YI
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 17, 2025

Hello,

I’ve recently reorganized our tasks by creating epics and dragging the relevant tasks under each corresponding epic.

However, I noticed that even after doing so, the tasks (e.g., WCE-41, WCE-93, WCE-37, WCE-36) are still showing up separately in the main project list view — in addition to appearing under their respective epics.

Could anyone advise how I can ensure that these tasks are displayed only once, ideally under the epic view only, and not duplicated in the main list?

Thanks!

 

   image.png

 

1 answer

3 votes
Yogesh Mude
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
July 17, 2025

Hello @Sedo YI Welcome to the community!

Assuming you are using project timeline view and in this case ensure you should select the Hierarchy From EPIC to STORY in the Filter.

Note: Make sure that each task should have its respective parent to be selected.

image.png

The same applicable for plans as well and if you are not using Timeline then please share your snpa so that it help us to check and assist you accordingly.