How to move story to Done column in active sprint view if there is any sub task?

tanmoydhara
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 26, 2018

Unable to move the story to 'Done' column if there is any sub task associated with the story, though story status is displaying as 'Done'. But if there is no sub task associated with the story, then we are able to move stories to 'Done' Column.

1 answer

0 votes
Jack Brickey
Community Champion
October 26, 2018

I suspect you have a blocking condition configured to prevent parent from being closed until all children are closed. Please see this article for more. 

Suggest an answer