How to link a workflow to a kanban board ?

Bernie Winter
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 27, 2020

I have setup a simple workflow for the cards status
Backlog
To Do 
In Progress

Done 

My Kanban board doesn't reflect the status even when I add the columns and assign the status to the columns. 

1 answer

0 votes
Joshua Sneed Contegix
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 27, 2020

Hi Bernie,
It is necessary to associate the workflow with the project and narrow the board's filter down appropriately before you will be able to associate statuses with columns. Cheers!

Bernie Winter
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 27, 2020

Hi Joshua
I have associated the workflow with the project and the board filter is only excluding done > 2 weeks.

When I add a new card it messages that the card has been added but can't be seen 