Hello, I am trying to figure out how to find all tasks which are not linked to any story while still have a connection to the Epic ...
thank you for you help
Hi Petr,
Try something like:
project = ABC AND issueLinkType is EMPTY and parent = ABC-1
where ABC-1 is the Epic key.