How do I change work log info? I made a mistake and now it shows 1 day for a 3 hour task. 

1 answer

0 votes
Kian Stack Mumo Systems
Community Champion
June 27, 2019

Alejandra,

Please navigate to the ticket where the wrong worklog is. On the bottom, you should see a box that says Comments, History, ect.

It'll say "Work Log" on it. Click that tab. Screen Shot 2019-06-27 at 5.20.16 PM.png

Find the incorrect worklog and click the Pencil icon to edit.

Screen Shot 2019-06-27 at 5.18.47 PM.png