It's not possible to change start date of closed sprint through the UI. Though you can make the change directly in DB, but making direct Db changes is something which is discouraged unless you have a strong business case.
Please read here - https://confluence.atlassian.com/jirakb/how-to-edit-the-dates-associated-with-a-closed-sprint-779159174.html
Hi Tarun,
Thanks for the suggestion. But it is necessary to change my Sprint start time as my velocity chart is not reflecting the commitment points of earlier sprints. That is probably because the sprint start time is earlier than the time when the issues were added to the sprint. Is there no other way than modifying the DB?
Thanks for your help.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.