Hi,
I'd like to always see the estimate and remaining estimate in hours instead of days.
If I change to the "Old view" the estimates are shown in hours, like this:
How can I get the same values in the "new view"?
This is what the new view looks like:
This is a known bug in the new issue view - see JRACLOUD-69310
There are a few workarounds mentioned on this issue:
Workaround
You can set your working days per week or working hours per day to a higher value than any one ticket's time log would reach. For example:
- Set your working hours per day to 1000 to replicate format=hours
- Set your working days per week to 100 to replicate format=days
AND/OR
There is the option of turning off the new detail view
Just remember if you do the first option (via Jira Settings > Issues > Time Tracking), this will edit the global settings for all issues / projects across your instance.
Ste
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.