Hello All, need your support to create a project plan in Jira that MUST show the plan including the following:
1. Major Tasks
2. Sub Tasks
3. Task Schedule (Start & Expected Completion)
4. Relationship among tasks (such as SS, SF, FS etc)
5. Task Ownership / Assignment
6. View all above along with Gantt Chart
In short, I want to prepare a project plan the way it is prepared in MS Project.
Can someone help me in it pls.? Thanks & Regards,
Hello Vivek,
Thanks for reaching out to Community!!
You can leverage Advanced Roadmaps feature for this. It supports task hierarchy, scheduling, dependencies, ownership, and provides a Gantt-style timeline view.
https://www.atlassian.com/software/jira/guides/advanced-roadmaps/overview#what-is-advanced-planning
Regards,
Archana