Hello,
I spen more than 2 hours not on trying to find out how to have instead of one row with columns To do, In progress and Done.
I want to have multiple rows where I have the first row with the column to contain all the highest priorities the secont row the medium and the third row the low ones.
I find a way to filter the issues by applaying a filter but thats not the look I'm going for.
This is how I want my board to look like - https://ibb.co/h7fRH6g
Thank you for your time.
Hi @Stefan Mihaylovski and welcome to the Community!
Those priority lines you see in the board are swimlanes. If your board is in a company managed software project, you can add them by going to board settings > swimlanes. Select queries as the option to create swimlanes by and then specify a filter for each priority value you want to see as a separate swimlane.
In team managed projects, swimlanes are not available on a board. And in business projects, you can use grouping to either display columns or statuses, but not both at the same time. So, in short, it depends what type of project you are using to see if what you are trying to do is possible.
Hope this helps!
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.