Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

How to change the finished states of subtasks of epics in a kanban board?

Thomas Lerch
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 5, 2020

Hi 

I have created a Kaban style board with several columns one of them is the "Finished" /"done" last column. 

In this board the main tasks are epics. How can I change the representation of subtasks of those epics. For each of the other columns I create one subtask per step. So the different states that I can set the subtasks  to make no sense other than "done" state.

Let's say you have a board that is about cleaning the floor. A different person does each subtask.

Board has these states: 

  • Vacuum Cleaning
  • Wipe Cleaning
  • Polishing
  • Finished state is called "The house is Clean".

The epic is Cleaning Jana's Mansion Entrance.

So now the Epic has 4 subtasks for each state.

Now those subtask only can only be set to these 4 above mentioned states in my jira. I just want to set the state of the subtask Vacuum Cleaning to finished. 

Because otherwise in the epic it will say "Status of "Vacuum Cleaning": The house is clean. But that's incorrect. A simple "Done" would be better. So state "The house is clean" makes no sense for the vacuum cleaning subtask.

Is this possible if I have a custom name for the "Finished" collumn in a board?

 

 

 

 

 

2 answers

0 votes
John Funk
Community Champion
June 7, 2020

Hi Thomas - Welcome to the Atlassian Community!

I am not sure that I completely following what you have setup and what you are trying to accomplish. So I have some questions first.

1. Is this a Next-gen project or a Classic Software project?

2. Why are you using Sub-tasks under an Epic and not Stories or other similar task level issue types?

3. I assume you have different workflows for the Epic and Sub-task workflows. How are those different? 

4. Finally, what is keeping you from moving the Sub-task to Done?

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 5, 2020

Hi @Thomas Lerch -- Welcome to the Atlassian community!

Reading over your explanation and questions, I am not understanding the problem you are trying to solve.  Let's try this:

Often when teams use epics and child items (tasks, stories, and bugs), there are two views on their process: the higher epic-level and the lower delivery-level (tasks, stories, and bugs). When you try to put both process levels on one board, it can be confusing and problematic.

Some things you describe as "states": vacuum cleaning, wipe cleaning, etc.

  • If those are status/column "states" on the board, I would expect a single work item to move, column to column, as the work is done
  • If instead those are sub-items of the parent, such as "Cleaning Jana's Mansion Entrance", I would only expect columns like ToDo, In Progress, and Done... with the work flowing across the board for each sub-item: vacuum cleaning, wipe cleaning, etc.

Would you clarify which case, or another, applies?  Thank you.

Best regards,

Bill

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
TAGS
AUG Leaders

Atlassian Community Events