Is there a way in Jira though which we can capture the timestamp between two statuses?
OR I want to capture the time taken in a particular status
Open->In-Progress->Done
I want to capture the time , the issue was in Open state.
When I change the transition from Open to In-Progress, time will get displayed.How we can achieve this is JIRA.
Hello,
You would need an app for it. For example, this one:
https://marketplace.atlassian.com/apps/1211499/issue-history-collector?hosting=cloud&tab=overview