Currently, we have two "Done" Category statuses in our Workflow:
Unfortunately, Cancelled items are not being hidden from the Next-Gen backlog on Sprint Complete (which is the behavior for the default status associated to the "Done" category)
This means, "Cancelled" items build up on the backlog. There isn't any way to get rid of them besides moving them to another project, or deleting them (which stinks, because some have context and might be reopened in the future)
You need to change the way you use the board.
Map the "cancelled" status into the "done" column on the board. The act of cancelling them means they are done so tell Jira that they're done by moving them into the last column.