Hi,
I am wandering how I would solve next feature - issue blocked by delivery time of an external supplier. So I would have tasks linked like this:
I wouldn't like for TASK-2 to be included in my sprints, or have story points, and I know that it is usually fixed time 6 to 8 weeks, and I would like to show that in the roadmap.
Something like "once TASK-1 is in done, TASK-3 will be blocked for at least 6 weeks", and no resources will be spent or dedicated during that time