Jira Cloud: I know this topic was already started in the past... however I cannot find a simple way to reach this goal.
Mixed up with screen, screen scheme, issue type, issue type screen, issue type scheme, issue type screen scheme...
Looking for help and/or a quick manipulation guideline would help a lot to achieve this:
MyStory must have field A, B,C.
MyStory has subtasks MyDev and MyDoc.
MyDev and MyDoc must have field D,E,F.
Whatever I tried, MyDev and MyDoc still gets field A,B,C when I look at them inside the project.
Thanks.
Instructions to achieve this below:
Create an Issue Type Screen Scheme to house both of these screen schemes - then:
^ This should do the trick. Note this is assuming you're using a Classic project / view - it's slightly different for Next-Gen / New User View. As you're mentioning screen schemes, etc I assume you will be using a classic project. For the new user view:
Ste
Thx Stephen. Yes I was using a Classic project.
This was the point I was missing: the MyStory issue type must have "subdefinition" to attach a specific screen to the subtask.
I initially created two Issue Type Screen Schemes: one for MyStory, one for both MyDev and MyDoc.
Great help from your side, bravissimo.