When creating a time line, jira provides editing or changing the time of the Epics. but when a child issue is added to a relevant epic in the timeline, jira does not allow to change the time. it is automatically set to the sprint time line which the issue is included.
Tried out by adding "Start Date" and "End date" configurations to the issues. but still the gantt chart is not changing and also the expandable icon appear when the mouse pointer hovers in the end of the pillar in epics are not appearing for child issues.
can I know that is there any change in settings or a permission to be granted to enable this feature to create timelines.
Hello @Themiya Dharmathilake
Welcome to the Atlassian community.
In the Timeline associated with a Scrum board the issues can be scheduled either automatically based on the sprint(s) to which they get assigned or based on Start and Due dates. You can change this setting by clicking the ... button in the upper right corner of the Timeline view and selecting Configure Timeline.
Hi @Trudy Claspill
Thank you for the reply. Can you please put the pathway to the above config change in settings
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can change this setting by clicking the ... button in the upper right corner of the Timeline view and selecting Configure Timeline.
That's it. That is the path.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks man, @Trudy Claspill i literally about to loss my patience and have been thinking about one thing that i should look for any alternatives. But here we are, after spending so much time into this i finally find the solution now i am feeling very relaxed.....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.