How to add the time tracking button ?

Peeali Sarkar February 9, 2018

I am unable to add the time tracking button in projects. Have followed all the steps mentioned in the support document however, unable to add it.

Please help in resolving. Also, is there a customer support number to contact you guys.

 

Thanks, Peeali

3 answers

0 votes
Jack Brickey
Community Champion
February 9, 2018

If you add an Original Estimate the time tracking area will then display on the view issue screen. You can then log time using the “+” symbol on the top right of time tracking area. You can also do this via a board in the detail area and there are shortcut keys as well. If you didn’t add the OE at creation you need to Edit the issue to add. 

Peeali Sarkar February 11, 2018

Jack- Thanks for the revert. I know this step. Problem lies in adding the time tracking field of "Estimation".

0 votes
Peeali Sarkar February 9, 2018

Hi Alexey,

When we create an issue, there is an option to estimate task, which can be configured via Time Tracking under Configure fields.

Trying to attach a screenshot, but unable.

0 votes
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 9, 2018

What do you mean by time tracking button? Could you provide a reference to the mentioned support document?

Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 9, 2018

You should add time tracking field to the create issue screen. Did you do that?

Peeali Sarkar February 11, 2018

That's where i am facing the problem. I am unable to add the time tracking field in the create issue screen. Followed all the steps mentioned in the help section, then also it is not coming.

Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 11, 2018

Do you mean that there is no Time Tracking field there? Then check if time tracking is on. You can read more info here:

https://confluence.atlassian.com/adminjiraserver072/configuring-time-tracking-828788203.html

Peeali Sarkar February 12, 2018

I followed all the steps mentioned in the confluence article you have attached. However, i can enter only estimation hours and when i log my actual hours, there is no reduction in estimation hours and only update i can see in log hours.

For example; If have estimation of 72 hours for a story point  for 2 weeks sprint and i have logged 8 hours for day 1, so my remaining hours should be (72-8=64 hours). However, my hours remain 72 hours only.

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 12, 2018

Could you show us a screen shot of the time-tracking box on the issue view for the issue where you've put in an estimate and logged work?

Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 12, 2018

There is no reduction in the Original Estimate field. It does not change, if you log time. The Remaining Estimate field changes. There are 2 fields: Original Estimate, Remaining Estimate. Original Estimate never changes. Remaining Estimate changes according to logged work

Peeali Sarkar February 12, 2018

Nic- I am unable to share the screenshot as well. Trying to attach it through the above icon provided but its not happening. Is there any other option through which i can share the screenshot.