How to add remaining estimate field into issue type?

passqc
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
March 2, 2021

1. I create a project with next-gen software type
2. On Project/ project setting/ Issue type: choice any type
3. I want to add some field to estimate time remaining or original for issue. But i can't find this field type.
Please help me action this case.
thanks!

 

2 answers

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 2, 2021

I assume you are talking about the system "remaining estimate" field?

If so, then this field is not a real field, it is actually a part of another field.  Jira will choose the most appropriate parts of this to show you depending on the context.

On your issue type configuration, look for the field called "time tracking" - that contains the remaining estimate, along with the original estimate and time logged.

Troy Anderson
Contributor
March 28, 2025

But it doesn't actually show except on mouseover, so it is useless.  

0 votes
Stanislav
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 2, 2021

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
FREE
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events