How to add "bars" to the JIRA Portfolio Roadmap

Will Robinson
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 17, 2020

We have recently moved over to the Portfolio basic roadmap in JIRA. Some of the Epic rows don't have a bar to indicate their time estimation. 

A bar appear when I add a new Epic but I was wondering how we get bars onto the existing rows. 

The bars are not over to the far left/right of the roadmap - they're just not in the view at all.

Image 46.png

1 answer

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 20, 2020

Hi @Will Robinson  -- Welcome to the Atlassian Community!

My understanding is the epics appear on the basic roadmap using the Start Date and Due Date as range values.  For your missing epics, have you checked those fields to see what is in them?

One way to check them at a glance would be to use a filter search on them displaying those columns.  For example:

project = yourProjectName AND issueType = Epic ORDER BY Rank


Best regards,

Bill