Hi,
Request your support how to create a field for Effort Variance (%) for Task and Sub-task. This is required for one of the project.
Value of the new field is based on the following calculation.
Effort variance = (Time spent - Original Estimate)/ Original estimate*100. Kindly revert for any clarifications.
Thanks and regards
Nirmalya
I strongly recommend Performance Objectives for Jira plugin to compute various KPIs.
There is a build-in work ratio field, but it doesn't consider subtasks. You can even use it in JQLs like workratio > 100 to find underestimated works. You may create a new custom field plugin by modifying its code.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.