How make a burnup chart to read issues in Testing column as completed?

Germaine Too Andreasen
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 29, 2024

The Testing column property has been set up the same as the Done column. However, the Burnup chart only takes issues in the Done column as completed. Is there anyway for it to read the issues in the Testing column as completed too?

2 answers

2 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 29, 2024

Welcome to the Atlassian Community!

No, it would not be a burnup chart if you could, because you only burn when something is done.

You could map the test column status into the done column though, that would give you the correct chart.

0 votes
Danut M _StonikByte_
Atlassian Partner
January 29, 2024

Hi @Germaine Too Andreasen,

You can also easily do this, without being necessary to alterthe configurtion of you agile board, by using the Sprint Burndown Burnup Chart gadget offered by our Great Gadgets app. 

This gadget has an option to define what "done" means and allows you to set specific statuses for considering an issue done. It should do the trick for you.

image.png

 

I hope this helps.

Disclosure: I am part of the team who develops this gadget. 

Thank you,

Danut Manda

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events