The Testing column property has been set up the same as the Done column. However, the Burnup chart only takes issues in the Done column as completed. Is there anyway for it to read the issues in the Testing column as completed too?
Welcome to the Atlassian Community!
No, it would not be a burnup chart if you could, because you only burn when something is done.
You could map the test column status into the done column though, that would give you the correct chart.
You can also easily do this, without being necessary to alterthe configurtion of you agile board, by using the Sprint Burndown Burnup Chart gadget offered by our Great Gadgets app.
This gadget has an option to define what "done" means and allows you to set specific statuses for considering an issue done. It should do the trick for you.
I hope this helps.
Disclosure: I am part of the team who develops this gadget.
Thank you,
Danut Manda
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.