How do you know an SLA ends recalculating to all Issues

Daniel Alonso
Contributor
January 19, 2023

Hi, I'm updating an SLA in an old project that has 38,373 Issues and I see this message.

Screenshot 2023-01-19 at 1.51.02 PM.png

Two questions:

1. Is there a way to know exactly when the SLA finishes to recalculate?

2. Is there a way to exclude certain Issues, let's say by date to be included in the recalculation?

 

1 answer

1 vote
Ismael Jimoh
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 19, 2023

Hi @Daniel Alonso 

To your questions:

  1. There’s no way to know. You’ll see the SLA on the issues related to it once the recalculation is done. To my knowledge no notification is sent for this.
  2. No there is none. Unless the issue doesn’t match the set of issues the SLA impacts or the issue is not done before the recalculation, all issues matching that don’t fulfil these criteria will be recalculated.
Daniel Alonso
Contributor
January 26, 2023

Good to know Ismael. Thank you.