How do story points marked as "done" get counted as "Done - story points" to complete SPRINT?
I have all user stories with status "Done". But they aren't counted as "Done - story points" at the top of the screen.
When I try to "Complete Sprint" Jira wants to move the stories to backlog or other sprint.
How can I Complete Sprint with User Stories recognised as done?
Welcome to community!
The statuses in the last column in the board is considered as done statuses.
Is Done status in your board's last column?
Thanks that's the solution. Much appreciated.