How do I move sprints up and down in the backlog view?

Rex Parsons
Contributor
July 26, 2022

In the Backlog view of a project, there used to be a 'move sprint up' and 'move sprint down' option on the three ellipses to the right.  That appears to be gone now and there is only Edit and Delete.  How do I re-order my sprints?

1 answer

0 votes
Trudy P Claspill
Community Champion
July 26, 2022

The ability to reorder sprints applies only to planned sprints, not active sprints. Are you looking at sprints that have already been started?

https://support.atlassian.com/jira-software-cloud/docs/plan-a-sprint/#Edit--reorder--or-delete-a-sprint